Setting Up a Manufacturing Subsidiary in India: Corporate and Regulatory Requirements
Foreign groups usually ask how to incorporate a manufacturing subsidiary in India. The better question is in what order four separate regimes touch it: company law, foreign exchange rules, sector and factory regulation, and tax. Most delays do not come from a missing form. They come from a decision under one regime that quietly breaks another. This piece walks through those pressure points in the order they tend to appear.
Why the Indian subsidiary must be an Indian company
Foreign parent companies often consider a branch or project office first. For manufacturing, that route is largely closed. Under the RBI’s rules for branch and liaison offices, a branch cannot carry out manufacturing or processing, except inside a Special Economic Zone. That leaves a locally incorporated subsidiary.
A Private Limited Company is the usual form. The parent holds nearly all the shares, and a nominee holds one share to meet the two-member minimum. The Companies Act, 2013 also requires at least one resident director, meaning someone who stayed in India for 182 days or more in the previous calendar year. Plan that appointment early. The resident director also becomes the practical contact for banks and regulators.
Entry route: automatic for most manufacturing, but trace the ownership chain
Manufacturing is, in most cases, open to 100 percent foreign investment under the automatic route, with no prior government approval. Some regulated sectors carry caps or conditions, so check the sector entry in the consolidated FDI policy first. The harder question is upstream ownership. Press Note 3 of 2020 requires government approval when the investor, or its beneficial owner, is situated in a country sharing a land border with India.
After the Cabinet decision of 10 March 2026, law-firm commentary reports that non-controlling beneficial ownership of up to 10 percent from such countries can enter through the automatic route. Above that level, approval is still needed. Specified manufacturing sectors are reportedly on a 60-day processing track.
In practice, this means mapping the parent’s shareholder chain, including funds and minority investors, before filing anything. A cap table that looks clean at the parent level can look different once beneficial owners are traced. A wrongly characterised investor can stall the project after the plant lease is already signed.
Capital inflow: pricing, timing and reporting
Foreign exchange rules turn the parent’s investment into a compliance calendar. Shares issued to a non-resident cannot be priced below fair value, supported by a valuation certificate from an eligible professional. Money must arrive through banking channels, and shares must be allotted within 60 days of receipt. If allotment misses that window, the funds generally have to be refunded. After allotment, the company reports the issue through the RBI’s reporting system, and the FC-GPR form is due within 30 days.
Late filing attracts a late submission fee and can complicate later fundraising or exit. Banks also ask for certified identity documents of the foreign investor, so keep them ready. Funding the plant with a parent loan is a different matter. External commercial borrowing rules then apply, along with transfer pricing scrutiny on the interest rate. That choice should be made before the first remittance, not after.
Incorporation mechanics with long-term consequences
Routine Company Registration filings through the Ministry of Corporate Affairs’ SPICe+ form are easy enough. The decisions behind them deserve more thought. The objects clause should describe manufacturing activities broadly enough to cover future product lines, because amending it later needs a special resolution and a fresh filing.
Authorised capital should match the plant’s funding plan, since stamp duty in many states is linked to it. The registered office address matters as well, because state-level approvals tie back to it. The company must also record its significant beneficial owners, and the parent’s ownership details feed directly into that disclosure.
Plant approvals: the labour code transition
The four labour codes were brought into force on 21 November 2025. The Occupational Safety, Health and Working Conditions Code replaced the Factories Act, 1948 along with a dozen other laws. Reports on the notification note that existing licences and state rules continue during the transition, and that some central and state rules were still being finalised. For a new plant, that creates a practical risk. The application route in one state may differ from another.
Before signing a lease, confirm whether the state has notified its rules and which portal handles factory registration. Environmental consent from the state pollution control board, fire clearance and local building permissions run in parallel. Each can decide the real start date of production.
Where incentives fit
Some new manufacturing ventures may qualify for recognition by the Department for Promotion of Industry and Internal Trade (DPIIT). StartUp India Registration can bring tax and compliance relief, but the test looks at innovation, age and turnover. It also excludes businesses formed by splitting or reconstructing an existing one. A subsidiary that simply carries on the parent’s existing product line may not qualify. Confirm the current conditions before building any benefit into the financial model.
A workable sequence
- Confirm the sector entry route and trace beneficial ownership.
- Appoint the resident director and incorporate.
- Open the bank account, receive the funds, and allot shares within 60 days.
- File FC-GPR within 30 days of allotment.
- Confirm state labour and environmental rules, then apply for plant licences.
None of these steps is difficult alone. The legal risk sits in the gaps between them, so one adviser should own the sequence from the first remittance to the first production run. The position above reflects October 2026, and each point should be verified against current notifications before acting.
Frequently Asked Questions
1. Can a foreign company manufacture in India through a branch office?
Ans. Generally no. A branch cannot carry out manufacturing or processing, except inside a Special Economic Zone. Most groups incorporate a wholly owned subsidiary instead.
2. Is government approval needed for 100 percent foreign ownership?
Ans. In most manufacturing sectors, no. The automatic route applies unless the sector is restricted or the investor’s beneficial ownership is caught by Press Note 3.
3. How soon must shares be allotted after the money arrives?
Ans. Within 60 days of receipt. If allotment is late, a refund is generally required. After allotment, the company reports the issue through FC-GPR within 30 days.
4. Do factory approvals still follow the Factories Act?
Ans. No longer in law. The Occupational Safety, Health and Working Conditions Code replaced it from 21 November 2025, though existing licences continue during the transition. Check your state’s current rules.